FRP PIPING SYSTEM - LNG Terminal in Vung Tau

  • Period: 12/2020 – 12/2021
  • Scope of work: Design, procurement, transportation, erection and commissioning (EPC) of FRP piping system to supply river water for Vaporizers system.

FRP Special Pipeline

  •  Size:
         Main Line: DN900
         Branch Line: DN650 & DN600
  • Pressure: Max. 10 Barg
  • Flow: 7500m3/h
  • Scope: EPC (Design, Calculation, Procurement, Erection, Testing & Commissioning)
 

OTHER PRODUCTS AND SERVICES

Design, supply, installation, and commissioning of Fire and Gas systems to monitor gas leaks and detect sparks, and hazardous heat sources for the entire LNG warehouse.
Fabrication, transportation, erection and commissioning of Metering Skid to measure gas flow before loading into storage tanks of LNG Terminal.
Fabrication, transportation, erection and commissioning of pump control cabinets to monitor operating parameters of 03 river water pumps supplying water to the cooling system.
Supplying materials, erection and testing the cabinet system to control, monitor the operating parameters of the fire pump station.

Provide solutions to monitor occupational safety, promptly respond to incidents that cause unsafe work on site, promptly support evacuation, rescue and warn to minimize the damage to the health of workers.